Northern Town of Creighton Sewer System Rehabilitation

Creighton, Saskatchewan

underwayWastewaterGIS
Federal contribution
$1.2M
$1,214,400
Federal share40%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2024
202420252026
BuiltForecast

Approved 9 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Northern Town of Creighton
Construction start
Oct 16, 2024(actual)
Construction end
Mar 31, 2026(forecast)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2024