Reconstruction of four Wellesley Township Roads

St. Clements, Ontario

completeHighways and RoadsMRIF
Federal contribution
$372,977
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
2006
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Wellesley
Construction start
May 1, 2005(actual)
Construction end
Dec 4, 2006(actual)

Against the original forecast

  • Construction end14 months lateforecast Sep 30, 2005