Back to projects

Improvements to Steffler Road

St. Clements, Ontario

completeHighways and RoadsCC
Federal contribution
$299,263
Federal share33%

of $897.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Wellesley
Construction start
Jul 27, 2009(actual)
Construction end
Oct 2, 2010(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 1, 2009
  • Construction end5 weeks lateforecast Aug 31, 2010