Purchase of a wheelchair accessible vehicle to continue transportation services provided by the Shuswap Association for Community Living in Salmon Arm, British Columbia.
Federal contribution
$94,000
Federal share74%
of $127.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 1, 2024
2025
Built
Approved 9 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Shuswap Association for Community Living
- Construction start
- Jul 1, 2024(actual)
- Construction end
- Jan 28, 2025(actual)
Against the original forecast
- Construction start7 months lateforecast Dec 1, 2023
- Construction end4 weeks lateforecast Dec 31, 2024