Active Transportation and Pedestrian Safety Plan for Stanley Mission, Saskatchewan.
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 10, 2026
202420252026
BuiltForecast
Approved 22 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Lac La Ronge Indian Band
- Construction start
- Jan 15, 2024(forecast)
- Construction end
- Dec 13, 2024(forecast)
Also in La Ronge
- Northern Town of La Ronge - Wastewater Treatment Plant Upgrades$7.1M
- Sewage Pumping Stations & Sewage Treatment Plant Upgrades$1.3M
- Lac La Ronge Provincial Park Potable Water Supply Upgrade$257.5K
- Northern Town of La Ronge - Community Recreation Trails Upgrade$86.1K
- Active Transportation and Pedestrian Safety Plan for Lac La Ronge$50.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121814 in the federal list. How to read these figures.