Sewage Pumping Stations & Sewage Treatment Plant Upgrades
Federal contribution
$1.3M
$1,337,000
Federal share33%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
20162017201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Northern Town of La Ronge
- Construction start
- May 16, 2016(actual)
- Construction end
- Nov 4, 2019(actual)
Also in La Ronge
- Northern Town of La Ronge - Wastewater Treatment Plant Upgrades$7.1M
- Lac La Ronge Provincial Park Potable Water Supply Upgrade$257.5K
- Northern Town of La Ronge - Community Recreation Trails Upgrade$86.1K
- Active Transportation and Pedestrian Safety Plan for Lac La Ronge$50.0K
- Active Transportation and Pedestrian Safety Plan for Stanley Mission, Saskatchewan.$50.0K