okimaw peyesew kamik - King Thunderbird Centre

Edmonton, Alberta

completeOtherGICB
Federal contribution
$21.0M
$21,000,000
Federal share56%

of $37.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 3, 2024
202420252026
Built

Approved 3 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Sep 25, 2023(actual)
Construction end
Jan 14, 2026(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2023
  • Construction end3 months lateforecast Oct 27, 2025

Also in Edmonton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121856 in the federal list. How to read these figures.