okimaw peyesew kamik - King Thunderbird Centre
Federal contribution
$21.0M
$21,000,000
Federal share56%
of $37.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 3, 2024
202420252026
Built
Approved 3 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- The Boyle Street Service Society
- Construction start
- Sep 25, 2023(actual)
- Construction end
- Jan 14, 2026(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2023
- Construction end3 months lateforecast Oct 27, 2025
Also in Edmonton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121856 in the federal list. How to read these figures.