BCC Phase 2 Capital

Toronto, Ontario

underwayCultureGICB
Federal contribution
$7.8M
$7,844,177
Federal share53%

of $14.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2024
today
2024202520262027
BuiltForecast

Approved 4 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Jan 29, 2025(actual)
Construction end
Mar 31, 2027(forecast)

Against the original forecast

  • Construction start15 months lateforecast Oct 16, 2023

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121882 in the federal list. How to read these figures.