Cap Aux Os Arts Centre

Gaspé, Quebec

underwayCultureGICB
Federal contribution
$1.6M
$1,647,682
Federal share41%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 6, 2025
20252026
BuiltForecast

Approved 11 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Jul 1, 2025(actual)
Construction end
Jun 30, 2026(forecast)

Against the original forecast

  • Construction start19 months lateforecast Nov 30, 2023

Also in Gaspé

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121893 in the federal list. How to read these figures.