Replacement of the exterior cladding and the roof (phase 1)

Gaspé, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$511,900
Federal share17%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 31, 2021(actual)
Construction end
Jun 30, 2022(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Jul 31, 2022

Also in Gaspé

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58969 in the federal list. How to read these figures.