Centre d’art Battat – CAB

Montréal, Quebec

underwayCultureGICB
Federal contribution
$10.2M
$10,227,308
Federal share49%

of $20.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 18, 2024
today
202520262027
BuiltForecast

Approved 7 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Centre d’art Battat
Construction start
Oct 21, 2024(actual)
Construction end
Jan 31, 2027(forecast)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2024

Also in Montréal