Back to projects

Purchases to support transit service for East Preston/Lawrencetown and Ship Harbour, Nova Scotia.

Musquodoboit Harbour, Nova Scotia

completePublic TransitRTSF
Federal contribution
$356,746
Federal share80%

of $445.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 10, 2024
20252026
Built

Approved 3 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Jul 1, 2024(actual)
Construction end
Feb 23, 2026(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2024
  • Construction end5 weeks earlyforecast Mar 31, 2026

Also in Musquodoboit Harbour

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121904 in the federal list. How to read these figures.