Purchase of vehicles and supporting infrastructure to expand door-to-door transit service for the communities of East Preston/Lawrencetown, Ship Harbour and rural communities in between in Nova Scotia

Musquodoboit Harbour, Nova Scotia

completePublic TransitRTSF
Federal contribution
$349,738
Federal share79%

of $440.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 22, 2023
20232024
Built

Approved 3 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Feb 27, 2023(actual)
Construction end
Jul 5, 2024(actual)

Against the original forecast

  • Construction start7 months lateforecast Aug 1, 2022
  • Construction end8 months lateforecast Oct 31, 2023