Purchases to continue transit service in Teulon, Rockwood and Woodlands, Manitoba.

Teulon, Manitoba

completePublic TransitRTSF
Federal contribution
$161,835
Federal share80%

of $202.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2025
2025
Built

Approved 11 months before the announcement.

Program
Permanent Public Transit Program
Construction start
May 18, 2024(actual)
Construction end
Oct 10, 2024(actual)

Against the original forecast

  • Construction start6 months lateforecast Nov 11, 2023
  • Construction end5 weeks earlyforecast Nov 11, 2024