Teulon - Handi-Van Purchase

Teulon, Manitoba

completePublic TransitPTIF
Federal contribution
$45,255
Federal share50%

of $91.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Teulon
Construction start
Aug 15, 2017(actual)
Construction end
Aug 24, 2017(actual)

Against the original forecast

  • Construction start5 months lateforecast Mar 23, 2017
  • Construction end4 months earlyforecast Dec 31, 2017

Also in Teulon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49265 in the federal list. How to read these figures.