Purchases to support transit service in Alberni-Clayoquot Regional District, British Columbia
Alberni-Clayoquot, British Columbia
Federal contribution
$762,000
Federal share76%
of $997.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 26, 2026
today
2025202620272028
BuiltForecast
Approved 15 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Regional District of Alberni-Clayoquot
- Construction start
- Nov 26, 2025(actual)
- Construction end
- Mar 31, 2028(forecast)
Against the original forecast
- Construction start8 weeks lateforecast Oct 3, 2025
Also in Alberni-Clayoquot
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 122188 in the federal list. How to read these figures.