Back to projects

Highway 4 - Tofino Area (Kennedy Lake)

Alberni-Clayoquot, British Columbia

completeHighways and RoadsISF
Federal contribution
$900,000
Federal share50%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 25, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 4, 2009(actual)
Construction end
Oct 16, 2009(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 1, 2009
  • Construction end2 weeks lateforecast Sep 30, 2009

Also in Alberni-Clayoquot

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28998 in the federal list. How to read these figures.