Purchases to support transit for Lac Seul First Nation, Ontario.
Federal contribution
$872,303
Federal share100%
of $872.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 11, 2025
today
202520262027
BuiltForecast
Approved 13 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Lac Seul First Nation
- Construction start
- Oct 28, 2024(actual)
- Construction end
- Mar 31, 2027(forecast)
Against the original forecast
- Construction start5 months lateforecast May 27, 2024
Also in Sioux Lookout