The partial electrification of the Legendre transportation centre
Federal contribution
$83.3M
$83,275,026
Federal share50%
of $166.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 22, 2025
today
202620272028
BuiltForecast
Approved 2 weeks before the announcement.
- Program
- Zero Emission Transit Fund
- Ultimate recipient
- Société de transport de Montréal (STM)
- Construction start
- Jan 1, 2027(forecast)
- Construction end
- Oct 31, 2028(forecast)
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 123395 in the federal list. How to read these figures.