Steinbach Industrial Park Development
Federal contribution
$500,000
Federal share9%
of $5.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 22, 2008
20092010
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Steinbach
- Construction start
- Jan 1, 2009(actual)
- Construction end
- Dec 31, 2009(actual)
Against the original forecast
- Construction start3.7 years lateforecast Apr 4, 2005
- Construction end3.2 years lateforecast Oct 31, 2006
Also in Steinbach
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12346 in the federal list. How to read these figures.