Underground Infrastructure Renewal Phases 2 & 3

Steinbach, Manitoba

completeDrinking WaterSCF
Federal contribution
$1.3M
$1,333,333
Federal share30%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
2016201720182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Steinbach
Construction start
May 23, 2017(actual)
Construction end
Oct 28, 2019(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Oct 8, 2019

Also in Steinbach