Ravensong Aquatic Centre Renovation
Qualicum Beach, British Columbia
Federal contribution
$7.0M
$7,000,000
Federal share24%
of $29.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2025
today
202620272028
BuiltForecast
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Regional District of Nanaimo
- Construction start
- May 1, 2026(forecast)
- Construction end
- Jan 31, 2028(forecast)
Also in Qualicum Beach
- Qualicum Beach - Berwick Water Supply Upgrade$1.1M
- Beach Creek Waterfront Walkway and Viewing Platform$1.0M
- The Water and Wastewater Portion of the Memorial Upgrade Phase 3$862.5K
- Qualicum Beach - Beach Creek Culvert Replacement at Crescent Road East$750.0K
- Nanaimo Regional District - Dunsmuir Community Park Phase 2 Improvements$296.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 123736 in the federal list. How to read these figures.