Nanaimo Regional District - Dunsmuir Community Park Phase 2 Improvements

Qualicum Beach, British Columbia

completeActive TransportationCVRIS
Federal contribution
$296,208
Federal share80%

of $370.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2021
2022
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 12, 2021(actual)
Construction end
Apr 30, 2022(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast May 31, 2022

Also in Qualicum Beach

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60568 in the federal list. How to read these figures.