YMCA Bridletowne Neighbourhood Centre
Federal contribution
$9.0M
$9,000,000
Federal share12%
of $77.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 22, 2025
today
20262027
BuiltForecast
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- YMCA of Greater Toronto Area
- Construction start
- May 31, 2025(forecast)
- Construction end
- Mar 31, 2027(forecast)
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 123774 in the federal list. How to read these figures.