Olds Mens Shed and Community Arts Hub: Activating the former Town of Olds Operations Shop
Federal contribution
$199,824
Federal share80%
of $249.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 22, 2025
2026
BuiltForecast
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Town of Olds
- Construction start
- Oct 29, 2025(actual)
- Construction end
- Apr 30, 2026(forecast)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2025