Resurfacing Highway 27

Olds, Alberta

completeHighways and RoadsISF
Federal contribution
$738,157
Federal share50%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jun 1, 2010(actual)
Construction end
Aug 26, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2010
  • Construction end5 months lateforecast Mar 31, 2011