Community Arena Complex

Grand Manan, New Brunswick

completeRecreationMRIF
Federal contribution
$1.1M
$1,134,085
Federal share33%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 28, 2007
20082009
Built

Approved 8 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Grand Manan
Construction start
Jul 6, 2007(actual)
Construction end
Mar 27, 2009(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Aug 1, 2007
  • Construction end9 months earlyforecast Dec 31, 2009

Also in Grand Manan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12405 in the federal list. How to read these figures.