Sand Dome - Rehabilitation Grand Manan

Grand Manan, New Brunswick

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$188,672
Federal share80%

of $235.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 5, 2021
2021
Built

Approved 8 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of New Brunswick
Construction start
Feb 18, 2021(actual)
Construction end
Nov 1, 2021(actual)

Against the original forecast

  • Construction start3 months earlyforecast May 24, 2021
  • Construction end2 months earlyforecast Dec 31, 2021