25th Street Upgrade
Federal contribution
$815,348
Federal share25%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 11, 2005
2006
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Saskatoon
- Construction start
- May 17, 2005(actual)
- Construction end
- Feb 28, 2006(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2005
- Construction end5 months lateforecast Sep 30, 2005
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12436 in the federal list. How to read these figures.