Back to projects

Water System Improvements

Riverside-Albert, New Brunswick

completeDrinking WaterMRIF
Federal contribution
$332,126
Federal share33%

of $996.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 1, 2006
2006200820102012
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Riverside-Albert
Construction start
Oct 18, 2005(actual)
Construction end
Mar 23, 2012(actual)

Against the original forecast

  • Construction start6 months lateforecast May 2, 2005
  • Construction end3 years lateforecast Mar 31, 2009

Also in Riverside-Albert

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12441 in the federal list. How to read these figures.