Watermain Renewals

Riverside-Albert, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$290,879
Federal share50%

of $581.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Riverside-Albert
Construction start
Sep 18, 2017(actual)
Construction end
Nov 17, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast May 23, 2017
  • Construction end8 months earlyforecast Jul 15, 2018

Also in Riverside-Albert

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48193 in the federal list. How to read these figures.