Back to projects

Lytton Fire and Emergency Services Centre

Lytton, British Columbia

approvedOtherGICB
Federal contribution
$23.1M
$23,142,640
Federal share100%

of $23.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 16, 2025
today
2026202720282029
BuiltForecast

Approved 6 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Village of Lytton
Construction start
Apr 1, 2027(forecast)
Construction end
Mar 31, 2029(forecast)