Village of Lytton Groundwater Development

Lytton, British Columbia

completeDrinking WaterCWWF
Federal contribution
$1.3M
$1,300,000
Federal share50%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018201920202021
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Lytton
Construction start
Jul 28, 2017(actual)
Construction end
Nov 30, 2020(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Sep 5, 2017
  • Construction end16 months earlyforecast Mar 31, 2022

Also in Lytton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49840 in the federal list. How to read these figures.