Back to projects

Russell Wastewater Treatment Upgrades

Russell-Binscarth, Manitoba

completeWastewaterMRIF
Federal contribution
$506,000
Federal share30%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2005
2006200720082009
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Russell
Construction start
Jun 2, 2005(actual)
Construction end
Mar 26, 2009(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 17, 2005
  • Construction end18 months lateforecast Oct 1, 2007

Also in Russell-Binscarth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12601 in the federal list. How to read these figures.