Russell-Binscarth Airport Resurfacing
Federal contribution
$369,792
Federal share60%
of $616.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2021
2022
Built
Approved 6 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Russel-Binscarth
- Construction start
- Sep 28, 2021(actual)
- Construction end
- Dec 31, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Sep 1, 2021