Regina Wastewater and Drainage Improvements

Regina, Saskatchewan

completeWastewaterMRIF
Federal contribution
$1.7M
$1,700,000
Federal share19%

of $9.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 4, 2005
20062007
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Regina
Construction start
May 17, 2005(actual)
Construction end
Dec 31, 2006(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2007