Back to projects

Sherbrooke Community League - Net Zero Retrofit

Edmonton, Alberta

approvedOtherGICB
Federal contribution
$823,122
Federal share80%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2026
202420252026
BuiltForecast

Approved 8 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Sherbrooke Community League
Construction start
Aug 1, 2023(forecast)
Construction end
Jul 1, 2024(forecast)

Also in Edmonton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 126944 in the federal list. How to read these figures.