Bridge Replacement
Federal contribution
$36,592
Federal share25%
of $146.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2005
200620072008
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Quill Lake
- Construction start
- Jul 31, 2005(actual)
- Construction end
- Dec 19, 2007(actual)
Against the original forecast
- Construction end21 months lateforecast Mar 31, 2006
Also in Quill Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12717 in the federal list. How to read these figures.