Back to projects

Wastewater Lagoon Expansion

Quill Lake, Saskatchewan

completeWastewaterSCF
Federal contribution
$244,879
Federal share33%

of $734.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 26, 2016
2017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Quill Lake
Construction start
Oct 15, 2016(actual)
Construction end
May 29, 2017(actual)

Against the original forecast

  • Construction start2 months earlyforecast Dec 15, 2016
  • Construction end4 months earlyforecast Sep 30, 2017