Wastewater Lagoon Expansion
Federal contribution
$244,879
Federal share33%
of $734.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 26, 2016
2017
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Quill Lake
- Construction start
- Oct 15, 2016(actual)
- Construction end
- May 29, 2017(actual)
Against the original forecast
- Construction start2 months earlyforecast Dec 15, 2016
- Construction end4 months earlyforecast Sep 30, 2017
Also in Quill Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46542 in the federal list. How to read these figures.