Back to projects

Road Reconstruction

Bethune, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$81,378
Federal share25%

of $325.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2005
20062007
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 31, 2006(actual)
Construction end
Oct 16, 2007(actual)

Against the original forecast

  • Construction start3 months lateforecast May 15, 2006
  • Construction end5 months earlyforecast Mar 31, 2008

Also in Bethune