Drainage Improvements

Bethune, Saskatchewan

completeWastewaterMRIF
Federal contribution
$4,829
Federal share25%

of $19.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2007
2007
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Bethune
Construction start
Dec 20, 2006(actual)
Construction end
Nov 5, 2007(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2007
  • Construction end5 months earlyforecast Mar 31, 2008