Water and Wastewater System Improvements

Blacks Harbour, New Brunswick

completeDrinking WaterMRIF
Federal contribution
$594,260
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 8, 2007
200820092010201120122013
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Blacks Harbour
Construction start
Aug 16, 2007(actual)
Construction end
Mar 25, 2013(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 1, 2007
  • Construction end3.6 years lateforecast Aug 30, 2009

Also in Blacks Harbour

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12760 in the federal list. How to read these figures.