Village Food Hub
Federal contribution
$472,560
Federal share40%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2023
20232024
Built
Approved 8 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Eastern Charlotte Waterways Inc.
- Construction start
- May 1, 2023(actual)
- Construction end
- Mar 31, 2024(actual)
Against the original forecast
- Construction start10 months lateforecast Jul 1, 2022
- Construction end9 months lateforecast Jun 30, 2023
Also in Blacks Harbour
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65615 in the federal list. How to read these figures.