Schedule

Announced and approvedAug 10, 2023
20232024
Built

Approved 8 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
May 1, 2023(actual)
Construction end
Mar 31, 2024(actual)

Against the original forecast

  • Construction start10 months lateforecast Jul 1, 2022
  • Construction end9 months lateforecast Jun 30, 2023