Mt. Sima Ski Lodge
Federal contribution
$517,050
Federal share30%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 18, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Whitehorse
- Construction start
- Oct 1, 2005(actual)
- Construction end
- Feb 28, 2008(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2005
- Construction end18 months lateforecast Sep 1, 2006
Also in Whitehorse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12784 in the federal list. How to read these figures.