WTP & System Upgrades
Federal contribution
$250,000
Federal share5%
of $4.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2005
200620072008
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Tisdale
- Construction start
- Aug 22, 2005(actual)
- Construction end
- Mar 20, 2008(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 1, 2005
- Construction end12 months lateforecast Mar 31, 2007