Lift Station and Lagoon Upgrade

Tisdale, Saskatchewan

completeWastewaterSCF
Federal contribution
$1.2M
$1,228,333
Federal share33%

of $3.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2018
201920202021
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Tisdale
Construction start
Apr 2, 2019(actual)
Construction end
Jul 22, 2021(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Mar 15, 2019
  • Construction end3 weeks lateforecast Jun 30, 2021