Loverna North - Clay Capping of Road
Federal contribution
$23,999
Federal share25%
of $96.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2005
2006
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Antelope Park
- Construction start
- Jul 31, 2005(actual)
- Construction end
- Oct 17, 2006(actual)
Against the original forecast
- Construction end7 months lateforecast Mar 31, 2006
Also in Marengo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12855 in the federal list. How to read these figures.