Back to projects

New Manhole and Gravity Mains Upgrade

Marengo, Saskatchewan

completeWastewaterCWWF
Federal contribution
$163,929
Federal share50%

of $327.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Marengo
Construction start
Jan 2, 2018(actual)
Construction end
Sep 17, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Nov 1, 2017
  • Construction end3 months earlyforecast Dec 31, 2018

Also in Marengo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50066 in the federal list. How to read these figures.