New Multi-Purpose Facility
Federal contribution
$250,000
Federal share4%
of $6.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 27, 2006
200620072008
Built
Approved 5 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Shaunavon
- Construction start
- Oct 31, 2006(actual)
- Construction end
- Mar 20, 2008(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2006
- Construction end12 months lateforecast Mar 31, 2007
Also in Shaunavon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12864 in the federal list. How to read these figures.