Back to projects

New Multi-Purpose Facility

Shaunavon, Saskatchewan

completeRecreationMRIF
Federal contribution
$250,000
Federal share4%

of $6.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 27, 2006
200620072008
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Shaunavon
Construction start
Oct 31, 2006(actual)
Construction end
Mar 20, 2008(actual)

Against the original forecast

  • Construction start7 months lateforecast Apr 1, 2006
  • Construction end12 months lateforecast Mar 31, 2007

Also in Shaunavon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12864 in the federal list. How to read these figures.