Town of Shaunavon Water UV Disinfection
Federal contribution
$410,400
Federal share40%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 5, 2019
20202021
Built
Approved 2 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Shaunavon
- Construction start
- Jun 15, 2020(actual)
- Construction end
- Dec 31, 2020(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 25, 2020
- Construction end8 weeks earlyforecast Feb 26, 2021
Also in Shaunavon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54512 in the federal list. How to read these figures.